TUZLA WASTEWATER TREATMENT PLAN 3rd PHASE PROJECT

Ongoing projects

Project Name : Tuzla Wastewater Treatment Plant 3. Phase Construction Project

Location : Tuzla / İstanbul

End Recipient : İstanbul Su ve Kanalizasyon İdaresi - ISKI

Contractor : AKTOR S.A

Start of Project : 2018

Contact Information
Detailed Description

Upgrade and extension of Tuzla Wastewater Treatment plant to eliminate nitrogen and phosphorus, activated sludge process shall be calculated in accordance with ATV-131E standards for phase 1, 2 and 3. All process and hydraulic calculations for phase 1, 2 and 3 shall be given in details (hydraulic profile of general sedimentation, water and sludge lines and water, sludge, air, wastewater, rainwater, drinking water and utility water, irrigation, etc. site piping plans and sections of lines, and P&I diagrams

Wastewater Design Flow Rates Phase 1, 2 and 3

Phase 1   QDW,d (m3/d) 150.000                       QWW,h (m3/h) 8.400 

Phase 2   QDW,d (m3/d) 75.000                         QWW,h (m3/h) 3.125

Phase 3   QDW,d (m3/d) 400.000                      QWW,h (m3/h) 22.200

MENA provided the following services:

  • Detailed design (final design) of WWTPs facilities
  • Soil Investigation
  • Geotechnical Report
  • Underground infrastructure mapping with NDT (Non-Destructive Testing) method
  • Preparation of Process Calculation and Report
  • Hydraulics calculation
  • Functional Design Specification
  • Detailed Structural design and calculations
  • Architectural design
  • Detailed MEP design and calculations
  • Sanitary projects
  • Electrical and Automation design
  • Full and in detail AutoCAD drawings (all related with process, general arrangement, architectural, civil and MEP including automation) single lines MCCs and Local control panels
  • Material take off for excavation, structural, architectural, mechanical and electrical works
  • As-Build Drawings
  • GIS Projects (Geographic Information Systems)
  • Plant Model
Project Location