ATAKÖY WASTEWATER TREATMENT PLANT

Completed Projects

Start Of Project: 1June 2016

End Of Project 15 May 2019

Biological Treatment Flow : 240.000 m3/day

Menbrane Treatment Flow : 30.000 m3/gün

Contractor :  FISIA & ALKATAŞ İNŞAAT ve TAAHÜT AŞ. JVC

Contact Information

Ataköy 8-9-10. Kısım Mah. Lale Sok. No 5/1/1 Bakırköy, İstanbul

Detailed Description

Purpose of Construction:

To treat the wastewater of Basaksehir, Kucukcekmece and Sultangazi districts with advanced biological methods.

Construction Features:

● Within the scope of the project, a Membrane Plant with a capacity of 30.000 cubic meters per day was built with an advanced biological waste water treatment plant with a capacity of 240.000 cubic meters per day. In addition, various revisions were completed at the first stage facility.

● The second stage of the facility will serve 1.100.000 people.

MENA has undertaken all structural and civil design of the Treatment Plant.

Project Location